For twelve months, New Zealand electricians could choose between the old and new editions of the standards cited in the Electricity (Safety) Regulations. That choice ended at the close of 12 November 2026. From 13 November 2026, only the newly cited editions count. If you install, inspect or buy solar and batteries, here is what that means in plain terms.
What actually changed
The Electricity (Safety) Amendment Regulations 2025 came into force on 13 November 2025. They updated which editions of the key standards the regulations point to, with a 12-month transition where either the previous or the newer edition could be used. For solar work, the headline updates were:
- AS/NZS 3000 (the Wiring Rules) moved from the 2007 edition to AS/NZS 3000:2018, including Amendments 1, 2 and 3, with New Zealand modifications.
- AS/NZS 5033 (PV arrays) moved from the 2012 edition to the 2021 edition.
- AS/NZS 4777.1 (inverter installation) moved to the 2024 edition.
- AS/NZS 3010 (generating sets) moved to the 2017 edition.
WorkSafe put it simply in March 2026: electricians could use either the 2007 or 2018 Wiring Rules until 12 November 2026, and after that date the 2018 standard becomes mandatory.
Batteries: AS/NZS 5139 comes in through the Wiring Rules
The battery installation standard, AS/NZS 5139, isn’t listed directly in the regulations. But AS/NZS 3000:2018 requires battery systems to comply with it, and the Electrical Workers Registration Board has confirmed that citing the 2018 Wiring Rules makes AS/NZS 5139 apply to battery energy storage installs (UPS systems aside). With the transition over, that’s now the baseline for every new home battery. It covers where a battery can go, separation from living areas, ventilation, protection and labelling, so expect your installer to talk about location early.
What about systems already on your roof?
You don’t need to rip anything out. The amendment includes a savings provision: installations that were already in place or under way before 13 November 2025 can keep being used and maintained, provided they aren’t electrically unsafe and they complied, and still comply, with the rules as they were at the time. Adding to a system, such as fitting a battery or extra panels, is new work, so ask your electrician which requirements apply to the new part.
If you’re getting quotes
- Ask whether the design was done to the current editions, especially if the quote was prepared before mid-November.
- For a battery, ask where it will go and why. Placement under AS/NZS 5139 is one of the most common reasons a design changes.
- Check your electrician holds the Mains Parallel Generation endorsement. It’s a separate requirement, explained in our endorsement guide.
If you’re an installer
Now is the time to retire any old-edition templates: design checklists, labelling sets, test sheets and commissioning records. Battery jobs deserve a fresh look at your standard placement options. The Installers Hub has the compliance calendar and the free rule changes cheat sheet, and the 2025–26 rule changes article sums up the wider picture.
This is a plain-language summary, not legal advice. Always work from the regulations and standards themselves.
Sources
Want an independent second opinion?
Before you sign a quote, get a straight read on it from someone who isn’t the one quoting you.
Talk to SolarLink