New grid connection rules from 1 December 2026: what changes

Every grid-connected solar or battery system needs the local lines company’s approval to connect. From 1 December 2026, the rules for how those applications work are changing. The Electricity Authority’s Network Connections Amendment, made in February 2026, rebuilds the distributed generation (DG) application processes in Part 6 of the Electricity Industry Participation Code. Here’s what changes and who it affects.

The big change: export power, not panel size

Until now, which process an application followed depended on the system’s nameplate capacity. From 1 December 2026, it depends on maximum export power: how much the system can actually push into the network. The Code defines it as either the nameplate capacity minus the minimum load at the connection point, or the limit set by an active export control device.

In practice, the Authority expects most applicants to work it out conservatively from the panel or inverter rating, because minimum load is usually close to zero at some point in the day. Where a hard export limit is set in the inverter, that limit can matter. The Authority’s guidance says that where an export limit could change which process applies, the network should talk it through with the applicant. So if you’re designing close to a threshold, have that conversation early.

The new tiers

  • 10 kW or less: a one-stage application (Process 1), or a simplified one-stage option (Process 1A) that the applicant can choose in specified circumstances. This covers most homes.
  • Above 10 kW and below 300 kW: a new two-stage process (Process 2), with an initial application and then a final one. The network must approve or decline a completed initial application within 40 business days, and the final application generally follows within 12 months of initial approval.
  • 300 kW and above: Process 3, which adds an interim stage. Networks must publish these applications in a connections pipeline so everyone can see the queue.

The Authority is clear that the timeframes in the Code are maximums, not targets. Networks are expected to process applications as quickly as they reasonably can.

Changing gear later means a new application

For the larger processes, the Authority decided that increasing nameplate capacity, or replacing components, needs a new application, even if the export figure doesn’t change. It’s worth knowing before a commercial client asks to swap inverters mid-project.

Already in the queue?

Larger applications started before 1 December 2026 under the old process can switch to the new one if both the applicant and the network agree. The applicant resubmits the application unchanged and the network fast-tracks it, using the assessment work already done.

What it means for you

  • Homeowners: very little day to day. A good installer still handles the application for you. How grid connection works explains the basics.
  • Farms, businesses and organisations: know your expected maximum export power before you approach the network, and build the two-stage process into your timeline. Our commercial feasibility service covers this.
  • Installers: check each network’s updated forms and connection standards, and confirm how they want maximum export power shown. Export limits are covered in the 10 kW shift.

Separate processes for large load connections (above 69 kVA) follow from 1 June 2027.

Sources

BL

Brad Lynch

An electrician with 15+ years in the trade and 7 specialising in solar, Brad founded SolarLink to close the knowledge gaps across the industry — from installers and builders to first responders and the community.

Independent advice

Want an independent second opinion?

Before you sign a quote, get a straight read on it from someone who isn’t the one quoting you.

Talk to SolarLink
Talk to Brad